CONSTRUCTION PROGRESS UPDATE
19 December 2019
Stage 2 Demolition of the existing core is well underway and on track to complete by March-April 2020.
Aqualand’s in-house construction team has completed the following key construction milestones prior to the year's end:
- Construction of the new stair and lift core is now complete with the new core lobby slabs and stairs poured to Level 18;
- Stage 2 demolition commenced in September, which is currently down to Level 8. We anticipate that Stage 2 demolition will be completed by March-April 2020.
- The southern podium precast panels have been installed and the structural slabs have been poured to Level 1 in the southern corner of the podium
- The installation of in-ground services in the basement level are underway.