Stage 2 Demolition of the existing core commences on the week commencing 23 September 2019.
Aqualand are due to commence Stage 2 Demolition of the existing concrete core on the week commencing 23 September 2019. Aqualand anticipate that Stage 2 demolition will continue until circa March-April 2020. The following demolition works will be undertaken during this time:
- Removal of the existing concrete core, located to the western elevation of the 61 Lavender St building, from top level down.
- Progressive dismantle of the scaffolding on the western elevation of the building.
- Removal of the existing precast concrete spandrel panel on the building’s western elevation.
We are also due to commence demolition of the basement 3 slabs on 18 September 2019. Sustained noise from jackhammering and saw cutting emanating from the basement levels are to be expected within the initial 1-2 weeks period. This will be followed by intermittent noisy works in the basements throughout the Stage 2 demolition phase.
All demolition works will be undertaken within the approved DA hours.