CONSTRUCTION PROGRESS UPDATE
13 July 2019
MILESTONE ACHIEVED: In June 2019 Aqualand completed the Stage 1 Demolition of the existing structure, making way for the new lift and stair core construction to progress unimpeded.
- New lift and stair core has been poured to level 4.
- Existing precast façade panels have been safely removed down to level 3.
- Scaffolding has been safely removed down to level 3 on the northern, eastern, and southern elevations.
- South Eastern corner demolition works will commence in July 2019 and will commence construction of the new slabs in August 2019.
- Stage 2 demolition (removal of the existing cores) is expected to commence in October 2019.