Stage 2 concrete structure is now at Level 14.
Aqualand's in-house construction team are progressing well with the following key construction milestones:
- Stage 2 concrete structure is now at Level 14
- Structural steel to slab extensions are now completed
- High Level services roughin are well underway throughout the building
- Façade installation has commenced with the northern balcony slider framing underway
- Internal partition framing has commenced
In the next quarter update you will see the following construction milestones achieved:
- Topping out of the concrete structure
- Commencement of the curtain wall façade
- Commencement of the luxury internal finishes
- Commencement of the kitchen installation
Despite the recent COVID 19 restrictions, we still remain on-track with our construction programme comprising a targeted date for commencing settlements in Q1, 2021.