  • CONSTRUCTION UPDATE: ASBESTOS REMOVAL WORKS

    2 November 2018

    Asbestos removal works will commence Monday 5 November 2018 to March 2019.

    Asbestos removal works will be undertaken between the hours of 8:00am and 5:00pm.  The works will be undertaken by Australasian Technical Services NSW Pty Ltd (asbestos removalist licence number 212177) under the supervision of the Principal Contractor H&R Hassarati Pty Ltd.

     

    SafeWork NSW was notified of this work on 22 October 2018.

     

    All asbestos removal works will be carried out in accordance with the relevant legislations and Council DA conditions.  As a minimum, the following safe work procedures will apply:

     

    • Signage, barriers and temporary fencing will be erected.
    • PVA solution or water will be applied to asbestos containing materials to mitigate dust.
    • Asbestos containing materials will not be broken, where possible.
    • Plastic will be used to cover horizontal surfaces and surrounds.
    • Asbestos containing material will be wrapped onsite and disposed of at an appropriate facility.
    • An independent party will undertake an inspection of the site on completion of the work and issue a clearance certificate.